Energy: a tax-equity flip, with the date derived

A tax-equity partnership whose flip date is derived from the investor's return rather than stated, reconciled against an external model.

Every number below is checked against an independent reference implementation on every commit — period by period, and on each metric, inside a declared tolerance. See benchmark methodology.

The case

A 100 MW-ac solar project financed through a tax-equity partnership. A tax investor funds 98% of the equity and takes 98% of the cash, the depreciation and the investment credit. When its after-tax return reaches 8%, the structure flips: the investor drops to 5% and the sponsor takes the rest.

The flip is not a date. It is a test, and when it lands depends on how the project performs — so the model derives it rather than stating it.

The reference

A national laboratory's open-source project-finance model, run in its leveraged-partnership-flip configuration. It publishes the flip year alongside both partners' cash, so the derived date is checkable and not only the split.

Not vendored. The tool was run once outside the repository and only its output numbers were carried across.

What it exercises

Packenergy
Declaredtwo typed assets, two parties, three states, one event, one waterfall
Language featuresa declared lifecycle, an event whose guard is a computed value, the transition log, a waterfall reading its owner's state
Conventions98/2 pre-flip and 5/95 post-flip sharing, an investment credit at 30%, MACRS on a basis reduced by half the credit, level-pay debt

The lifecycle sits on the partnership interest rather than the plant: the panels do not change when the structure flips, the claim on their cash does.

The test needs no solver. The criterion is an internal rate of return reaching 8%, which this language cannot compute mid-model. It does not need to — at a fixed hurdle the two statements are one:

IRR through period n >= 8%   <=>   NPV at 8% through period n >= 0

A discounted running sum is a recurrence, so the test is arithmetic evaluated once a period. Nor can it be circular: the test at period t reads flows through t-1, and every one of those periods is still pre-flip by construction, so the sharing percentages it depends on are settled before it is evaluated.

The result

The flip date is derived, and it agrees. The transition fires at period 4 against the reference's stated flip in year 3 — the same instant under the deal's own convention, where the year's books close, the return is tested, and the new sharing applies to the year that follows.

Both partners' cash reproduces across all 25 operating periods, through the flip and through the debt cliff at periods 18 and 19.

Asserted: two columns period by period, plus the transition itself.

The delta

Worst disagreement across all 25 periods and both columns: 1.0e-6 dollars, which is the engine's own publication precision rather than a convention difference.

Period 0 is not asserted. The reference books a sponsor development fee at close that this case does not model, and it has no bearing on the flip.

A variant the reference does not publish

The same deal on a monthly grid flips ten months earlier, in the second month of year 3.

By the end of year 2 the investor is $445,000 short of its hurdle, and two months of operating cash clear it — but an annual grid has no period between month 24 and month 36 in which to notice, so the event cannot fire until the next year end. The investor keeps 98% of the cash for ten months it was no longer entitled to, worth about $3.5mm here.

The grid is therefore an economic assumption whenever an event decides who gets paid, not a presentation choice. No external source publishes the monthly answer, so it is carried as a fixture rather than as a benchmark.

The model

version 0.1
model "tax-equity-flip"
use pack "energy" version "0.1.0"
time calendar annual from 2026-01 for 26

// A TAX-EQUITY PARTNERSHIP FLIP, where the flip date is DERIVED.
//
// A tax investor funds most of the equity and takes 98% of the cash and the
// tax attributes. When its after-tax return reaches a target, the structure
// flips: it drops to 5% and the sponsor takes the rest. The flip is not a date
// in a contract — it is a test, and when it lands depends on how the project
// performs.
//
// So the flip is a LIFECYCLE, and the date is an output. The partnership
// interest is declared with the `energy.flip_structure` lifecycle, opens in
// `pre_flip`, and an event moves it when the test passes.
//
// THE TEST NEEDS NO SOLVER. The criterion is an internal rate of return
// reaching 8%, and this language cannot compute an IRR mid-model. It does not
// need to: at a fixed hurdle the two statements are the same one.
//
//     IRR through period n >= 8%   <=>   NPV at 8% through period n >= 0
//
// A discounted running sum is a recurrence, which is a declared state, so the
// test is arithmetic evaluated once a period — a discrete test rather than a
// search, the same shape as an ordered waterfall's tiers.
//
// AND IT CANNOT BE CIRCULAR. The test at period t reads flows through t-1, and
// every one of those periods is by construction still pre-flip: the flip has
// not fired yet, or the test would not still be running. So the sharing
// percentages the test depends on are settled before it is evaluated.

entity asset project : Energy.Asset.GenerationFacility {
  technology         = "solar_pv"
  nameplate_capacity = 100000.0
  state operating
}

// The lifecycle lives on the INTEREST, not the plant. The panels do not change
// when the partnership flips; the claim on their cash does.
entity asset interest : Energy.Asset.ProjectInterest {
  interest_type = "tax_equity"
  state pre_flip
}

entity party sponsor      : Party { name = "Sponsor" }
entity party tax_investor : Party { name = "Tax investor" }

// ---------------------------------------------------------------------------
// The deal
// ---------------------------------------------------------------------------

assume energy_year_one = 250000000.0     // kWh in the first operating year
assume ppa_price       = 0.045           // $/kWh
assume ppa_escalation  = 0.02
assume degradation     = 0.005

assume capacity_kw     = 100000.0
assume om_per_kw       = 15.0
assume om_escalation   = 0.02

assume debt_amount     = 60000000.0
assume debt_rate       = 0.06
assume debt_term       = 18.0

// The equipment is $100mm; the reference capitalises $3.1mm of financing into
// the installed cost, so the credit and depreciation are taken on the larger
// figure. Both bases follow from it: the credit on all of it, depreciation on
// it less half the credit, which is the rule that catches people out.
assume installed_cost  = 103100000.0
assume itc_rate        = 0.30
assume tax_rate        = 0.21

assume preflip_share   = 0.98
assume postflip_share  = 0.05

assume hurdle          = 0.08
assume investor_equity = 42238000.0      // 98% of $43.1mm of equity

// ---------------------------------------------------------------------------
// The project, before anybody is paid
// ---------------------------------------------------------------------------

state project_cash {
  init 0.0
  next inputs.energy_year_one * inputs.ppa_price
        * pow(1.0 + inputs.ppa_escalation, time.t - 1.0)
        * pow(1.0 - inputs.degradation, time.t - 1.0)
       - inputs.capacity_kw * inputs.om_per_kw
        * pow(1.0 + inputs.om_escalation, time.t - 1.0)
       - if(time.t <= inputs.debt_term,
            0.0 - pmt(inputs.debt_rate, inputs.debt_term, inputs.debt_amount),
            0.0)
}

// THE TEST, as one recurrence.
//
// At period t this holds the investor's discounted after-tax position through
// period t-1: its share of cash, of the tax saved on the loss depreciation
// creates, and of the credit in the first operating year.
//
// It is one state rather than two because a state's `next` may read another
// state's PREVIOUS value and not its current one — so the flow of period t-1
// is exactly what is reachable here, and that is the flow the closed test
// wants. The lag is the deal's own convention: the year's books close, the
// return is tested, and the new sharing applies to the year that follows.
//
// Computed at the PRE-FLIP shares, and it stops accumulating the moment it
// turns non-negative — which is the period the flip fires. A test that has
// passed has no further question to answer, and stopping it keeps the series
// readable: its final value is the position that triggered the flip, not a
// running total at shares that stopped applying.
//
// Interest comes from `ipmt` rather than from a balance carried alongside.
// A balance state would hold the CLOSING figure, and interest is charged on
// the opening one — an off-by-one this states outright rather than works
// around.
state investor_npv_closed {
  init 0.0 - inputs.investor_equity
  next prev
       + if(time.t >= 2.0 and prev < 0.0,
            inputs.preflip_share
             * ( prev.project_cash
                 - inputs.tax_rate
                   * ( prev.project_cash
                       + if(time.t - 1.0 <= inputs.debt_term,
                            (0.0 - pmt(inputs.debt_rate, inputs.debt_term, inputs.debt_amount))
                            + ipmt(inputs.debt_rate, time.t - 1.0, inputs.debt_term,
                                   inputs.debt_amount),
                            0.0)
                       - macrs_rate(time.t - 2.0, 5)
                         * (inputs.installed_cost
                            - 0.5 * inputs.itc_rate * inputs.installed_cost) )
                 + if(time.t - 1.0 == 1.0, inputs.itc_rate * inputs.installed_cost, 0.0) )
             / pow(1.0 + inputs.hurdle, time.t - 1.0),
            0.0)
}

event flip when state.investor_npv_closed >= 0.0 {
  set entity asset.interest.status = "post_flip"
}

// ---------------------------------------------------------------------------
// What each partner receives
//
// The waterfall is owned by the INTEREST, so its steps read the lifecycle that
// governs the split. The investor takes its share and the sponsor takes the
// residual, which is what "the sponsor gets the rest" means.
// ---------------------------------------------------------------------------

waterfall interest.distribution on entity asset.interest {
  schedule every year from 2027-01 to 2051-01
  from state.project_cash

  pay investor to party.tax_investor =
        remaining * if(entity.state.status == "post_flip",
                       inputs.postflip_share,
                       inputs.preflip_share)
  pay sponsor  to party.sponsor = remaining
}

Run configuration

{ "deterministic": { "annual_discount_rate": 0.08 } }

Verified results

Checked period by period: 2 series across 25 periods, each within ±0.01 of the reference.

  • interest.distribution.investor
  • interest.distribution.sponsor